MA – L2 – Q51 – Decision Making Techniques

Terra Works Limited is a company that is engaged in site clearance and site preparation work. Information about its operations is as follows:
(1) It is Terra Works Limited’s policy to hire all the plant and machinery it needs rather than to purchase its own plant and machinery.
(2) Terra Works Limited will enter into an advance hire agreement contract for the coming year at one of three levels – high, medium, or low – which correspond to the requirements of a high, medium, or low level of orders obtained.
(3) The level of orders obtained will not be known when the advance hire agreement contract is entered into. Probabilities have been estimated by management as to the likelihood of the orders being at a high, medium, or low level.
(4) Where the advance hire agreement entered into is lower than that required for the level of orders actually obtained, a premium rate must be paid to obtain the additional plant and machinery required.
(5) No refund is obtainable where the advance hire agreement for plant and machinery is at a level in excess of that required to satisfy the site clearance and preparation orders actually obtained.
A summary of the information relating to the above points is as follows:

Level of Sales orders Probability Revenue GH¢000 Variable costs GH¢000 Plant and machinery hire costs
Advance GH¢000 Conversion GH¢000
High 0.25 15,000 10,500 2,300 1,500
Medium 0.45 8,500 5,950 1,500 850
Low 0.30 4,000 2,800 1,000
Low to medium 850
Medium to high 1,300
Low to high 2,150

Required:
(a) Prepare a table showing the outcomes for each decision and outcome combination.
(b) Prepare a pay-off matrix and determine the advance hire contract that maximizes the expected value.

 

(a) Outcomes

Decision Outcome Turnover GH¢000 Variable cost GH¢000 Advance hire GH¢000 Conversion premium GH¢000
Low Low 4,000 2,800 1,000 0
Medium 8,500 5,950 1,000 850
High 15,000 10,500 1,000 2,150
Medium Low 4,000 2,800 1,500 0
Medium 8,500 5,950 1,500 0
High 15,000 10,500 1,500 1,300
High Low 4,000 2,800 2,300 0
Medium 8,500 5,950 2,300 0
High 15,000 10,500 2,300 0

(b) Pay-off matrix

Decision Low (x=) GH¢000 Medium (x=) GH¢000 High (x=) GH¢000 Expected value (∑px) GH¢000
Probability (p) 0.30 0.45 0.25
Low 200 700 1,350 712.5
Medium (300) 1,050 1,700 807.5
High (1,100) 250 2,200 332.5

The highest expected value is earned if the medium advance hire usage contract is signed.