- 1 Marks
AA – L2 – SA – Q4.8 – PFM System Weaknesses
Question
PEFA performance assessment report?
A Ministries, departments and agencies experience delays in receiving cash funds for approved projects
B Lack of independent quality reviews
C Expenditure commitments being made outside the approved budget
D Revenue administration is weak
Answer
B
Explanation:
The 2018 PEFA assessment for Ghana’s Public Financial Management (PFM) system identified weaknesses such as delays in cash fund disbursements, unauthorized expenditure commitments, and weak revenue administration. However, a lack of independent quality reviews was not highlighted as a specific weakness in the report. Option B is the correct answer.
- Tags: ICAG, PEFA Assessment, Public Financial Management, Public Sector
- Level: Level 2
- Topic: Public sector audit
- Uploader: Salamat Hamid