The amount of time during which a path of activities could be delayed without affecting the overall project duration is called:

A. Independent float
B. Total float
C. Free float
D. Excess time float
E. Average time float

Answer:
B. Total float

Explanation:
Total float (or total slack) refers to the total time that a project task can be delayed without affecting the project’s overall completion date. It is crucial for project management as it helps in scheduling and resource allocation.

 