Wazobia is a construction company currently undertaking two separate contracts. From the following information relating to the just-concluded financial year and other data extracted from the records of the company, you are required to prepare accounts for the two contracts using a columnar format:

Contract WXYZ002 Contract WXYZ003
Contract Price ₦5,000,000 ₦3,500,000
Material Purchased ₦1,650,000 ₦950,000
Plant & Machinery Transferred to Site ₦4,500,000 ₦3,000,000
Wages Paid ₦1,460,000 ₦1,200,000
Other Expenses ₦900,000 ₦460,000
Wages Accrued ₦140,000 ₦100,000
Value of Work Certified ₦2,950,000 ₦1,800,000
Cost of Work Not Certified ₦1,600,000 ₦1,450,000
Plant & Machinery Written Down ₦3,600,000 ₦2,400,000
Material on Site C/F ₦850,000 ₦100,000