Skip to content
knowsia logo
  • Home
  • Programs
    • Student Dashboard
    • Professional Tuition
    • Webinars and CPDs
    • Certificate Courses
    • All Courses
  • Question Bank
    • Past Questions
    • Case Studies
    • Study Questions
    • QB Pricing
  • Knowsia AI
  • Community
  • Blog
  • About
  • My Account
  • Home
  • Programs
    • Student Dashboard
    • Professional Tuition
    • Webinars and CPDs
    • Certificate Courses
    • All Courses
  • Question Bank
    • Past Questions
    • Case Studies
    • Study Questions
    • QB Pricing
  • Knowsia AI
  • Community
  • Blog
  • About
  • My Account
knowsia logo
  • Home
  • Programs
    • Student Dashboard
    • Professional Tuition
    • Webinars and CPDs
    • Certificate Courses
    • All Courses
  • Question Bank
    • Past Questions
    • Case Studies
    • Study Questions
    • QB Pricing
  • Knowsia AI
  • Community
  • Blog
  • About
  • My Account
  • Home
  • Programs
    • Student Dashboard
    • Professional Tuition
    • Webinars and CPDs
    • Certificate Courses
    • All Courses
  • Question Bank
    • Past Questions
    • Case Studies
    • Study Questions
    • QB Pricing
  • Knowsia AI
  • Community
  • Blog
  • About
  • My Account
  • 20 Marks

MI – May 2021 – L1 – SB – Q2 – Costing Methods

Preparation of contract accounts and financial position for Segelu Nigeria Limited.

  • ICA (Nigeria)
  • PROFESSIONAL PROGRAM
  • MANAGEMENT INFORMATION
Question

Segelu Nigeria Limited is a construction company located in Bukuai Local Government. The company commenced the construction of a health centre building on 3 January, 2018 for a contract price of N30,000,000 with completion date of February 2019. Estimated cost of the contract was N21,000,000. The construction company’s financial year end was 30 September 2018, with the following balances extracted from the books of accounts on that date.

Description Amount (N)
Materials issued to site 3,220,000
Materials returned from site 250,000
Wages of workers paid 1,250,000
Own plant in use on site (at cost) 2,200,000
Plant hire and scaffolding 1,050,000
Head office expenses 1,220,000
Supervisory staff: direct 485,000
Supervisory staff: indirect 480,000
Value of work certified to 30 September 2018 16,200,000
Cost of work not yet certified 2,150,000
Progress payments 12,150,000
Material on site 30 September 2018 580,000
Workers’ wages due but unpaid 125,000
Depreciation on plant is to be provided at the rate of 15% per annum on cost.

You are required to prepare:
a) The contract account as at 30 September 2018 assuming the contract commenced 3 January 2018.
b) Contractee account.
c) An extract from the construction company’s financial position at 30 September 2018. (Total 20 Marks)

Answer

a) Contract Account for the year ended 30 September 2018

Description Amount (N) Description Amount (N)
Materials issued to site 3,220,000 Materials returned from site 250,000
Wages paid 1,250,000 Materials at site c/d 580,000
Wages accrued 125,000 Plant on site c/d 1,952,500
Plant at cost 2,200,000 Cost of work certified 5,097,500
Hiring of plants 1,050,000 Cost of work not yet certified 2,150,000
Supervisory staff: direct 485,000
Supervisory staff: indirect 480,000
Head office expenses 1,220,000
Total 10,030,000 Total 10,030,000
Cost to date 5,097,500 Value of work certified 16,200,000
Profit taken (wki) 5,551,250
Profit suspense c/d 5,551,250

b) Contractee Account

Description Amount (N) Description Amount (N)
Value of work certified 16,200,000 Payment on account 12,150,000
Balance c/d 4,050,000
Total 16,200,000 Total 16,200,000

c) SEGELU CONSTRUCTION LIMITED
Statement of Financial Position Extract

Description Amount (N)
Non-current Assets:
Plant at cost 2,200,000
Less depreciation 247,500
Total Non-current Assets 1,952,500
Current Assets:
Material on site 580,000
Work-in-progress 648,750
Total Current Assets 1,228,750
Current Liability:
Accrued wages 125,000
Total Liabilities 125,000
Net Assets 3,056,250

 

  • Tags: Construction, Contract Account, Financial Position, Segelu Nigeria Limited
  • Level: Level 1
  • Topic: Costing Methods
  • Series: MAY 2021
  • Uploader: Kwame Aikins
Back to all questions
knowsia

Take control of your business data with insight and in-depth understanding by taking this course. 

Our Offerings

  • Professional Tuition
  • Question Bank
  • CPDs and Webinars
  • Corporate Trainings
  • Certificate Courses
  • Zoom Meetings

Contact Info

  • +233203701923
    +233543919232
  • info@knowsia.com

My Account

  • My Account
  • Manage Subscriptions
  • Tutors Dashboard
  • Become An Affiliate
  • Affiliate Dasboard
  • Login/Logout

Get In Touch

Follow us on our social media and get daily updates.

Facebook-f Twitter Linkedin-in Envelope

Forgot Password?

admin

Sign In

Pick a Form

Professional Tutor Application Form
Academic Tutor Application Form
Student Tutor Application Form